CTT provided civil and structural design services, and marine
services for this 60 million gallons per year biofuel processing facility.
The process creates diesel fuel from vegetable oil. A 4,000 SF
office/control lab, a 2,500 Maintenance building, a 2,200 boiler building,
and various other supporting buildings are proposed.
Duties consisted of parking and drive layout, truck unloading
layout, sanitary sewer pump station, gravity sewer, sanitary sewer force
main connecting to City sewer on City Street, new waterlines, storm drainage
and, oil / water separation. Due to floodplain requirements, retaining
walls were used to elevate the site and building pads. A wet stormwater
detention pond is used for stormwater treatment.
Permitting duties included City Planning, City Board of
Adjustment, City Sewer Pretreatment, City and State Water, City and State
Sewer, City Stormwater, City Landscaping, City Traffic, City Trees, City
Fire, USACE Wetlands, USACE Pond Outfall Pipe, County Erosion Control.
NCDENR Sewer, NCDENR Coastal Management, NCDENR Waterlines, and NCDENR
Stormwater.
|

|