Photo taken at 80% complete
|
CTT provided
provided
the
study and design for the replacement of the existing, deteriorated, timber
bulkhead around the marina. The timber was replaced with approximately 850
LF of vinyl sheet piling and 2,400 vertical LF of timber mooring piles.
The bulkhead utilized helical earth anchors instead of the traditional
deadman anchors due to the limited easement behind the bulkhead. The
existing bulkhead was left in place.
CTT
produced complete design plans, specifications, and contract documents as
well as holding a bid letting, assisted in negotiations with the selected
contractor, and provided limited construction phase services.
|